Japan approves 4.9 km westward extension of Utsunomiya Light Line, targeting March 2036 service

Japan's transport minister approved the implementation plan for a 4.9 km westward extension of the Utsunomiya Light Line on October 9. The route would run from JR Utsunomiya Station's east entrance to Kyoiku Kaikan-mae; the city plans 14 additional trainsets and a March 2036 start of service.
Route and approval
The approved section runs 4.9 km from Miyamirai at JR Utsunomiya Station's east entrance to Komaoi 1-chome near Kyoiku Kaikan-mae. Utsunomiya City and Haga Town will own and build the track, while Utsunomiya Light Rail will operate the service. Under the applicable law, approval of this plan is deemed to grant the tramway business franchise.
Fleet and timetable
The city's plan calls for 14 low-floor trainsets based on the existing fleet. The ministry estimates construction at ¥69.8 billion before tax and plans trains every six minutes at morning and evening peaks and every ten minutes off peak. March 2036 is the planned opening, not a service date already confirmed by the approval.