South Korea publishes plan to move 31 central government bodies to Sejong by 2031

A stone sign marks the entrance to Government Complex Sejong in South Korea, with red-leaved trees and a glass-fronted building beyond.
Government Complex Sejong in Sejong Special Self-Governing City, South Korea (2014 reference photo). Photo by Minseong Kim (CC BY-SA 4.0). Resized and converted to WebP.

South Korea’s Ministry of the Interior and Safety issued a notice on November 24 to move 31 central administrative agencies and other government bodies to Sejong Special Self-Governing City by 2031. The plan covers 5,460 authorized positions. The first 22 bodies will move by 2027. A further notice will cover 13 other bodies whose relocation depends on legal amendments or related steps.

22 bodies (1,600 posts) move to leased sites by 2027. Nine (3,860 posts) move to new buildings by 2031. A further notice for 13 bodies (4,469 posts) will follow legal changes and related steps.
AITMONDO graphic based on primary sources.

31 bodies to move in two phases

Of the 44 bodies the government identified for relocation on October 13, the notice covers 31 that can move under existing laws. It followed consultation with experts and relevant departments, as well as public hearings. The staffing figures are based on authorized civil service positions as of September 29, 2026. The first 22 bodies, including the Korea Media and Communications Commission and the Personal Information Protection Commission, have a combined 1,600 authorized positions. They will move to leased premises, including privately owned buildings, by 2027.

Nine bodies to move to new buildings by 2031

Nine bodies that need their own buildings or specialized facilities, including the Board of Audit and Inspection, the Corruption Investigation Office for High-ranking Officials and the National Police Agency, will move into newly built offices by 2031. They have a combined 3,860 authorized positions. The ministry estimated that moving into leased premises will cost about 48.2 billion won and that constructing the new offices will cost about 1.6 trillion won.

Further notice for the remaining 13 bodies after legal changes and related steps

The current notice excludes 13 bodies with a combined 4,469 authorized positions. They include agencies whose moves require legal amendments and affiliated bodies that will move with them. The government plans to proceed with the amendments and publish a further notice based on when the legal changes take effect and when offices can be secured. The ministry says it will keep consulting the affected bodies, finalize each relocation schedule and provide advance notice.